15. LIQUIDATED DAMAGES**(**损失的清算)

15.1 Liquidated Damages for Delayed Delivery(延迟交货的违约赔偿金)

In case there is a delay in the delivery of the Equipment beyond the date of delivery specified in the Contract due to reasons attributable to the Seller, the Buyer is entitled to claim liquidated damages per day of delay in an amount equivalent to one tenth of one percent (0.1%) of the contract amount including V.A.T. of the Unit of Supply to which the delayed Equipment Such liquidated damages shall not exceed five percent (5%) of the contract amount including V.A.T.

如果由于卖方原因导致设备交货延迟,超过了合同规定的交货日期,则买方有权要求违约赔偿金,其额度为每延迟一天赔偿合同总金额的千分之一(0.1%),且应包含供货部件的增值税在内。对于交货延迟的设备,这种违约赔偿金总额不应超过包含增值税在内的合同总价的5%。

15.2 Liquidated Damages for Delayed Issuance of Preliminary Acceptance Certificate (初步验收证书延迟发出的赔偿金)

In order to meet the Target Date, the last Preliminary Acceptance Certificate shall be issued by (TARGET DATE). In case there is a delay in the issuance of the last Preliminary Acceptance Certificate beyond the above date due to reasons attributable to the Seller, the Buyer is entitled to claim liquidated damages per full week, i.e., seven (7) days of delay in an amount equivalent to two-tenths of one percent (0.2%) of the Contract Price including V.A.T. Such liquidated damages shall not exceed five percent (5%) of the Contract Price including V.A.T.

为了与预定日期相符,最后一份初步验收证书应在预定日期当日发出,即 年 月 日。如果由于卖方原因导致最后一份初步验收证书延迟发出,超过上述日期,则买方有权要求违约赔偿,即每延迟一周(七天)需赔偿包括增值税在内的合同价格0.2%。这种违约赔偿金不应超过包含增殖税在内的合同价格的5%。

14.2 Preliminary Acceptance Test (PA Test)(初步验收测试(PA Test))

A. On completion of construction and installation of any Operating Unit, the Buyer shall inspect and check the readiness for placing into operation of the said Operating Unit. The inspection and check by the Buyer shall be carried out in accordance with the Seller’s written instructions. The Seller, having confirmed and been satisfied with the readings and the result of the inspection and check, shall notify in writing the Buyer of the date of the PA Test of each Operating Unit.

在任何操作单元的建造和安装完成后,卖方应对该操作单元进行检验,确定其是否已准备就续,可以进行正常运行。买方应按照卖方的书面说明进行检验。在对检验结果进行验证并满意之后,卖方应以书面形式将每一个操作单元的初步验收测试日期通知买方。

B. If the Seller fails to notify the Buyer of the date of the PA Test within three (3) months from the date on which the above inspection and check on any Operating Unit was conducted, the Seller shall be deemed to have failed to perform and fulfill its obligations under the Contract and the Buyer may have recourse to the remedies as provided for in Article 14.4.A.

如果在对上述操作单元的检查和测试之日起的三个月内,卖方未能通知买方初步验收测试日期,则可认为卖方未能履行其合同所规定的职责和义务,买方可以按照14.4A条要求赔偿。

14.4 Remedies For Failure of Performance Guarantee

(对于性能保证失败的补救措施)

A. If the Seller is deemed to have failed to fulfill its obligations under the provisions of Article 14.2.B, 14.2.F, 14.2.H and 14.3.G, the Buyer may, at the expense of the Seller, make necessary corrections or adjustments, or make good the deficiencies. The Seller shall reimburse the expense incurred by the Buyer upon receipt of the Buyer’s invoice. If the Seller fails to make such payment to the Buyer within thirty (30) days from the date of receipt of the said invoice, the Buyer may, at its option, withdraw the said expense out of the Warranty Bond established under Article 17 hereof without prejudice to other remedies provided for in this Contract.

如果依据第14.2.B, 14.2.F, 14.2.H 和14.3.G条规定,买方认为卖方未能履行其义务,买方可以对缺陷进行必要的修正、调整或修复,费用由卖方负责。卖方应在收到发票后偿还买方因此而产生的费用。如果卖方在收到上述发票后三十天内未能向买方支付该款项,则买方有权选择在不损害本合同规定的其它赔偿的条件下,在此处第17条规定的质量保函中扣除上述费用。

15.3 Any liquidated damages payable in accordance with Article 15.1 & 15.2 hereof shall be deducted from the amount that the Buyer shall pay to the Seller under this Contract. In case that there is no amount that should be paid by the Buyer, the Buyer is entitled to withdraw the liquidated damages from the Performance Bond and/or Warranty Bond and/or Refund Bond established by the Seller under Article 17 hereof, in the event that the Seller fails to make any such payment within thirty (30) days from the date of receipt of the Buyer’s invoice. The Buyer’s right to claim such liquidated damages shall not affect any other rights or remedies the Buyer may have under this Contract.

依据此处第15.1和15.2条应支付的任何违约赔偿金都应从买方根据合同将要付给卖方的钱款中予以扣除。如果买方已经对卖方没有付款责任,且如果卖方未能在收到买方票据之日起三十天内支付该款项的话,买方有权依从据此处第17条建立的卖方开立的的履约保证金和/或质量保证金和/或预付款保证金中扣除违约赔偿金。买方要求这种违约赔偿金的权利不应对其依据本合同所享有的任何其它权利或赔偿产生影响。

国际商事合同笔记 - 本文屬於一個選集。
§ : 本文

相關文章

国际商事合同笔记 第二章Part5合同价格与付款条件

·1324 字·3 分鐘
4. CONTRACT PRICE AND PAYMENT TERMS**(**合同价格与付款条件) 4.1 The Contract Price is made on a fixed price basis and consists of the prices for all the supplies and services in the Article 3.1 hereof. However, the Contract Price is subject to any valid adjustments made through the application of the relevant provisions in the Contract.

国际商事合同笔记 第二章Part4合同范围

·391 字·1 分鐘
3. SCOPE OF CONTRACT**(**合同范围) 3.1 The Seller shall provide the following supplies and services under the terms and conditions of the Contract as more fully set out in the Contract Specifications: 卖方应根据合同条款提供下列供货和服务,详见技术合同:

国际商事合同笔记 第二章Part3合同生效日期

·340 字·1 分鐘
2. EFFECTIVE DATE OF CONTRACT**(**合同生效日期) 2.1 The Contract shall become fully effective and binding upon both parties hereto on the date on which all of the following conditions have occurred and been fulfilled: 满足下列条件后,该合同生效并对合同双方产生约束:

国际商事合同笔记 第二章Part2定义条款

·2320 字·5 分鐘
1. DEFINITIONS**(**定 义) In the Contract (as defined below) the words and expressions defined below shall have the meanings assigned to them, except where the context requires otherwise: (in alphabetic order) 在合同(具体如下文)中,对于本条所定义的词语和表述,其意义均应以定义为准,但上下文语境有特殊要求的除外。(按字母排序)

国际商事合同笔记 第二章Part1

·2111 字·5 分鐘
GENERAL TERMS AND CONDITIONS FOR CONTRACT (I) 合同一般条款(I) March, 2005 2005年3月 Procurement Department XX Co., Ltd. 采购部 XX设备工程服务有限公司 CONTRACT(合 同) This Contract made and entered into this (DATE) day of (MONTH), 2005 by and between XX Co., Ltd., a corporation duly organized and existing under the laws of the People’s Republic of China, with its principal office at Sanxing Riverside Development Zone, Zhangjiagang City, Jiangsu Province, the People’s Republic of China (hereinafter referred to as the “Buyer”) and (COMPANY NAME), a corporation duly organized and existing under the laws of the People’s Republic of China, with its principal office at, (COMPANY ADDRESS), the People’s Republic of China (hereinafter referred to as the “Seller”).

Contract Formation and Classification

·805 字·2 分鐘
A contract is, first of all, an agreement. It is a mainifestation of the mutual assent of the parties. The mutual assent, or the agreement, is typically reached when one part ( the offeror) makes an offer to another party ( the offeree ) who accepts the offer. Offer and acceptance are the acts by which the parties come to a “meeting of the minds”. When there is no meeting of the minds, there is no vaild contract. To determine whether the minds have met, both offer and acceptance must be analyzed. The offeror may have had something in mind quite different from that of the offeree. Notwithstanding, the intention of the parties is determined not by what they think, but by their outward conduct; that is, by what each leads the other reasonably to believe.